Verified Field Case StudyFeatured ExecutionRepair

Building Repair

Non-destructive rebound hammer survey, high-tensile rebar rust passivation, and structural micro-concreting.

Bhilwara, Rajasthan
July 2026
12 Columns
Building Repair
Verified Execution
Execution Profile

Project Information & Parameters

Client / Property Type

Commercial Complex

Specialization

Repair

Project Location

Bhilwara, Rajasthan

Area Treated

12 Columns

Execution Duration

14 Days

Completion Date

July 2026

Project Status

Successfully Completed & Warranty Active

Case Study Overview

Project Overview

Non-destructive rebound hammer survey, high-tensile rebar rust passivation, and structural micro-concreting.

Initial Site Diagnostics

The Problem & Structural Challenges

Carbonation-induced rebar corrosion and concrete spalling across 12 ground-level structural load-bearing columns, compromising structural integrity.
Engineering Deliverables

Scope of Work Executed

  • Non-destructive rebound hammer & ultrasonic pulse velocity survey
  • Selective chipping and concrete surface preparation
  • Zinc-rich rust inhibitor passivation on exposed reinforcement
  • Shear anchor installation and supplementary high-yield steel ties
  • Shrinkage-compensated polymer micro-concrete column jacketing
  • Anti-carbonation protective elastomeric coating
Technical Remediation

Engineered Solution & Methodology

Implemented structural micro-concreting and column jacketing using high-early-strength shrinkage-compensated repair mortars. Restored structural load ratings in compliance with IS 456 & IS 15988 codes.
Outcome & Handover

Results & Warranty Documentation

Structural compression load restored to 100% design capacity. Non-destructive post-cure testing confirmed zero internal voids and total adhesion integrity.