Verified Field Case StudyFeatured ExecutionRepair
Building Repair
Non-destructive rebound hammer survey, high-tensile rebar rust passivation, and structural micro-concreting.
Bhilwara, Rajasthan
July 2026
12 Columns
Verified Execution
Execution Profile
Project Information & Parameters
On-Site Logged
Client / Property Type
Commercial Complex
Specialization
Repair
Project Location
Bhilwara, Rajasthan
Area Treated
12 Columns
Execution Duration
14 Days
Completion Date
July 2026
Project Status
Successfully Completed & Warranty Active
Case Study Overview
Project Overview
Non-destructive rebound hammer survey, high-tensile rebar rust passivation, and structural micro-concreting.
Initial Site Diagnostics
The Problem & Structural Challenges
Carbonation-induced rebar corrosion and concrete spalling across 12 ground-level structural load-bearing columns, compromising structural integrity.
Engineering Deliverables
Scope of Work Executed
- Non-destructive rebound hammer & ultrasonic pulse velocity survey
- Selective chipping and concrete surface preparation
- Zinc-rich rust inhibitor passivation on exposed reinforcement
- Shear anchor installation and supplementary high-yield steel ties
- Shrinkage-compensated polymer micro-concrete column jacketing
- Anti-carbonation protective elastomeric coating
Technical Remediation
Engineered Solution & Methodology
Implemented structural micro-concreting and column jacketing using high-early-strength shrinkage-compensated repair mortars. Restored structural load ratings in compliance with IS 456 & IS 15988 codes.
Outcome & Handover
Results & Warranty Documentation
Structural compression load restored to 100% design capacity. Non-destructive post-cure testing confirmed zero internal voids and total adhesion integrity.